I need the calculation and mathemathical steps for the following question: B . Minimum Cost Schedule ( 2 5 points ) . Information concerning a
I need the calculation and mathemathical steps for the following question: B
Minimum Cost Schedule
points
Information concerning a project is given in the table below.
Activity Normal Time
days
Normal Cost
$
Crash Time
days
Crash Cost
$
Immediate Predecessor
s
A
B
C
A
B
D
B
E
C
D
F
E
G
E
H
G
Indirect project costs amount to $
per day. The company will incur a $
per day penalty for each day the project lasts beyond day
a
What is the project
s duration if only normal times are used?
b
What is the minimum
cost schedule?
c
What is the critical path for the minimum
cost schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started