I need this done fast! . Andrea just employed a new manager for her web business. The manager is new and would like to determine
I need this done fast!
. Andrea just employed a new manager for her web business. The manager is new and would like to determine the variable and fixed costs associated with work completed between January to June. Calculate the cost for the past six months Show all calculations
Month | Number of website hits | Customer website costs |
January | 15,900 | $9,000 |
February | 17,300 | $9,860 |
March | 14,500 | $8,600 |
April | 16,100 | $8,800 |
May | 17,100 | $8,600 |
June | 15,500 | $8,100 |
Required:
1. Using the high-low method, estimate the variable cost per website hit and the monthly fixed costs associated with the customer website 3 marks .
2. Using the high-low method, determine the monthly fixed costs associated with the customer website 4 mraks .
3. If Andrea expects 18,000 website hits for July, what are their anticipated customer website costs for July? 4 marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started