Question

1 Approved Answer

I need to create and discuss a Work Breakdown Structure (WBS). summary of the project : The ASP construction company has an opportunity to take

I need to create and discuss a Work Breakdown Structure (WBS).

summary of the project :

The ASP construction company has an opportunity to take on a project to build a horse barn located in Los Altos Hills, CA. A traditionally constructed wooden barn is requested by the client due to the weather condition of the location, with the project budget set as $135,000. The client owns a community barn called the Dream Horse Barn and requires a new ten-stall barn as a new addition to the 15 acres of land since the facility is a breeding, training, and horse-riding center.

project tasks :

Task Name
Pre-Planning - Research and Design
Research building codes, zoning regulations, restrictions, and permits
Barn layout
Barn ventilation
Permitting
Apply for building codes
Apply for zoning regulations
Apply for any needed permits
Acquire Materials
Foundation materials
Barn exterior materials
Roof materials
Additional materials for storage
Site Preparation
Remove organic materials
Check site for proper drainage, water availability and electricity
Build Foundation
Use fill materials to build a high level foundation
Finish top layer with desired barn flooring
Install Supporting Structures
Install Trusses
Install roof support beams
Install roof, doors, and windows
Build Additional Features

project scope :

High-level project scope

  • A build of 10 stall barn, 3,600 Square foot
  • Materials to use are woods and metal
  • Budget cost not to exceed $135,000
  • Timeline not to exceed five-months
  • Materials to be purchased by the project team and project work is to be completed by our team, no outsourcing

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics

Authors: Robert A Donnelly, Robert Donnelly Jr

2nd Edition

0133852288, 9780133852288

More Books

Students also viewed these General Management questions

Question

Subjective norms, i.e. the norms of the target group

Answered: 1 week ago

Question

The relevance of the information to the interpreter

Answered: 1 week ago