I want correct answer with proper explanation Show all your work A future project has an uncertain finish time and the finish time follows a

I want correct answer with proper explanation

Show all your work

A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 37 weeks, and the project variance is 7 weeks. If the project deadline is set to be 13 weeks, then what is the probability that the project would need more than the given deadline to complete?

Input should be either 1 or 2, with 1 represents "more than 50%" and 2 represents "equal or less than 50%".

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hotel Revenue Management

Authors: Dave Roberts

1st Edition

1637421915, 978-1637421918

More Books

Students also viewed these General Management questions

Question

What is meant by the compensation term line of sight? LO.1

Answered: 1 week ago

Question

2. Are they aware of the assumptions they are making?

Answered: 1 week ago

Question

Question 3

Answered: 1 week ago

Question

=+What can I do to make this press worthy?

Answered: 1 week ago