i. What affect would an increase in the duration of activity H of 6 days have on the project completion date? Explain your answer. ii.


Screenshot (46).png


i. What affect would an increase in the duration of activity H of 6 days have on the project completion date? Explain your answer. 

ii. What affect would an increase in the duration of activity H of 3 days have on the project completion date? Explain your answer. 

 

1a) Based on the Network Diagram below: (i) Identify and calculate the Early Start, Early Finish, Late Start, Late Finish and Float. (4 points) (ii) Highlight the Critical Path(s). (1 points) (iii) What is the duration of the project? (1 points) (iv) How many paths does the network diagram contain, and what is the duration of each path? (6 points) Activity B 8 Activity A Activity C 19 Activity G Activity E 16 15 Activity D Activity F 1 Activity H Activity J 2 Activity I

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions

Question

If X has distribution function F(t) = 0, t Answered: 1 week ago

Answered: 1 week ago