IBM uses activity-based costing to allocate overhead costs. The following data is available: Activity Cost Pool ($) Cost Driver Cost Driver Volume Machine Setup $180,000
IBM uses activity-based costing to allocate overhead costs. The following data is available:
Activity | Cost Pool ($) | Cost Driver | Cost Driver Volume |
Machine Setup | $180,000 | Number of setups | 450 |
Quality Inspections | $220,000 | Number of inspections | 550 |
Packaging | $120,000 | Number of units | 1,200 |
Calculate the overhead rate for each activity.