ID Activity Duration Predecessors 1 Baseball Stadium 2 Clear stadium site 70 days 3 Demolish building 30 days 2 4 Set up construction site 70
ID | Activity | Duration | Predecessors | |
1 | Baseball Stadium | |||
2 | Clear stadium site | 70 days | ||
3 | Demolish building | 30 days | 2 | |
4 | Set up construction site | 70 days | 3 | |
5 | Drive support piling | 120 days | 2 | |
6 | Pour lower concrete bowl | 120 days | 5 | |
7 | Pour main concourse | 120 days | 3,6 | |
8 | Install playing field | 90 days | 3,6 | |
9 | Construct upper steel bowl | 120 days | 3,6 | |
10 | Install seats | 140 days | 7,9 | |
11 | Build luxury boxes | 90 days | 7,9 | |
12 | Install jumbotron | 30 days | 7,9 | |
13 | Stadiuminfrastructure | 120 days | 7,9 | |
14 | Construct steel canopy | 75 days | 10 | |
15 | Light installation | 30 days | 14 | |
16 | build roof supports | 90 days | 6 | |
17 | Construct roof | 180 days | 16 | |
18 | Install roof tracks | 90 days | 16 | |
19 | Install roof tracks | 90 days | 17,18 | |
20 | Inspection | 20 days | 8,11,13,15,19 |
draw a network for Shoreline Stadium and determine the critical path for the project. Which activities are critical in this project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started