Question

1 Approved Answer

ID Activity Duration Predecessors 1 Baseball Stadium 2 Clear stadium site 70 days 3 Demolish building 30 days 2 4 Set up construction site 70

ID Activity Duration Predecessors
1 Baseball Stadium
2 Clear stadium site 70 days
3 Demolish building 30 days 2
4 Set up construction site 70 days 3
5 Drive support piling 120 days 2
6 Pour lower concrete bowl 120 days 5
7 Pour main concourse 120 days 3,6
8 Install playing field 90 days 3,6
9 Construct upper steel bowl 120 days 3,6
10 Install seats 140 days 7,9
11 Build luxury boxes 90 days 7,9
12 Install jumbotron 30 days 7,9
13 Stadiuminfrastructure 120 days 7,9
14 Construct steel canopy 75 days 10
15 Light installation 30 days 14
16 build roof supports 90 days 6
17 Construct roof 180 days 16
18 Install roof tracks 90 days 16
19 Install roof tracks 90 days 17,18
20 Inspection 20 days 8,11,13,15,19

draw a network for Shoreline Stadium and determine the critical path for the project. Which activities are critical in this project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essential Quantitative Methods For Business Management And Finance

Authors: Les Oakshott

7th Edition

1352005697, 978-1352005691

More Books

Students also viewed these General Management questions