ID Activity Duration Predecessor(s) 1 Clear stadium site 70 days - 2 Demolish existing building 30 days 1 3 Set up construction site 70 days

ID Activity Duration Predecessor(s) 1 Clear stadium site 70 days - 2 Demolish existing building 30 days 1 3 Set up construction site 70 days 2 4 Drive support piling 120 days 1 5 Pour lower concrete bowl 120 days 4 6 Pour main concourse 120 days 3,5 7 Install playing field 90 days 3,5 8 Construct upper steel bowl 120 days 3,5 9 Install seats 140 days 6,8 10 Build luxury boxes 90 days 6,8 11 Install jumbotron 30 days 6,8 12 Stadium infrastructure 120 days 6,8 13 Construct steel canopy 75 days 9 14 Light installation 30 days 13 15 Build roof supports 90 days 5 16 Construct roof 180 days 15 17 Install roof tracks 90 days 15 18 Install roof 90 days 16,17 19 Inspection 20 days 7,10,11,12,14,18 20 Cleanup 21 days 19 Exercise: Develop the network diagram for the Shoreline Baseball Stadium Project using the details provided in the table above. Carry out the Forward and backward Passes. Determine the critical path(s). Within 500 words, share your personal experience and lessons learned while carrying out the exercise.

image text in transcribed
Shoreline Baseball Stadium Project. ID Activity Duration Predecessor(s) 1 Clear stadium site 70 days 2 Demolish existing building 30 days 1 3 Set up construction site 70 days 2 4 Drive support piling 120 days 1 5 Pour lower concrete bowl 120 days 4 6 Pour main concourse 120 days 3,5 7 Install playing field 90 days 3,5 8 Construct upper steel bowl 120 days 3,5 9 Install seats 140 days 6,8 10 Build luxury boxes 90 days 6,8 11 Install jumbotron 30 days 6,8 12 Stadium infrastructure 120 days 6,8 13 Construct steel canopy 75 days 9 14 Light installation 30 days 13 15 Build roof supports 90 days 5 16 Construct roof 180 days 15 17 Install roof tracks 90 days 15 18 Install roof 90 days 16,17 19 Inspection 20 days 7,10,11,12,14,18 20 Cleanup 21 days 19 Exercise: Develop the network diagram for the Shoreline Baseball Stadium Project using the details provided in the table above. Carry out the Forward and backward Passes. Determine the critical path(s). Within 500 words, share your personal experience and lessons learned while carrying out the exercise

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Systems Analysis and Design

Authors: Scott Tilley, Harry J. Rosenblatt

11th Edition

1305494601, 9781305533936 , 978-1305494602

Students also viewed these General Management questions