Question

1 Approved Answer

Identify two tasks that do not belong to the critical path. Why aren't they on the critical path? Do not write the name of the

Identify two tasks that do not belong to the critical path. Why aren't they on the critical path? Do not write the name of the task. Instead, write the number of the task that appears in the first column, on the left side of the Gantt chart.

image
 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Perce... 34% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Name Project Envision Interview program stakeholders Develop project proposal Approve project proposal Establish project team Apply for research grant Plan Stakeholder analysis Develop ethics application Approve ethics application Lessons learned activity Develop PMP Approve PMP Execute Arrange bookings, flights etc Develop interview protocol Create workshop activites Interview participants Deliver workshops Evaluate project Close Wrap up project Release project team Duration Start 81 days 11/07/22 8:00 AM 35 days 11/07/22 8:00 AM 5 days 11/07/22 8:00 AM 15 days 18/07/22 8:00 AM 0 days 8/08/22 8:00 AM 5 days 8/08/22 8:00 AM 10 days 15/08/22 8:00 AM 21 days 29/08/22 8:00 AM 5 days 29/08/22 8:00 AM 10 days 5/09/22 8:00 AM 5 days 19/09/22 8:00 AM 1 day 26/09/22 8:00 AM 10 days 29/08/22 8:00 AM 0 days 9/09/22 5:00 PM 33 days 12/09/22 8:00 AM 2 days 12/09/22 8:00 AM 1 day 14/09/22 8:00 AM 1 day 14/09/22 8:00 AM 5 days 15/09/22 8:00 AM 10 days 22/09/22 8:00 AM 15 days 6/10/22 8:00 AM 3 days 27/10/22 8:00 AM 2 days 27/10/22 8:00 AM 1 day 31/10/22 8:00 AM Finish 31/10/22 5:00 PM 26/08/22 5:00 PM 15/07/22 5:00 PM 5/08/22 5:00 PM 8/08/22 8:00 AM 12/08/22 5:00 PM 26/08/22 5:00 PM 26/09/22 5:00 PM 2/09/22 5:00 PM 16/09/22 5:00 PM 23/09/22 5:00 PM 26/09/22 5:00 PM 9/09/22 5:00 PM 9/09/22 5:00 PM 26/10/22 5:00 PM 13/09/22 5:00 PM 14/09/22 5:00 PM 14/09/22 5:00 PM 21/09/22 5:00 PM 5/10/22 5:00 PM 26/10/22 5:00 PM 31/10/22 5:00 PM 28/10/22 5:00 PM 31/10/22 5:00 PM Predecessors 3 4 5 6 7 9 10 11 3 13 14 16 16 17 19 20 21 23 ul 2022 Oct 2022 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 Aug 2022 Sep 2022 23 8/08 10/09 Nov 2022 30 06 13

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

2 and 19 Task 2 Envision and task 19 Create workshop activities are no... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Data Mining

Authors: Pang Ning Tan, Michael Steinbach, Vipin Kumar

1st edition

321321367, 978-0321321367

More Books

Students also viewed these General Management questions

Question

=+b) What is the interpretation of the coefficient for Pedro Start?

Answered: 1 week ago

Question

What are the key elements of a system investigation report?

Answered: 1 week ago