Identifying, assessing, and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities? (Points :
Identifying, assessing, and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities? (Points : 5)
Conflict management
Risk and change management
Team management
Customer relations
Technical problem solving