If a company took 100 hours to assemble their first unit and 85 hours to assemble the second unit, we might expect it to take:
If a company took 100 hours to assemble their first unit and 85 hours to assemble the second unit, we might expect it to take: 72.25 hours to assemble the third unit. 72.25 hours to assemble the fourth unit. 70 hours to assemble the fourth unit. 70 hours to assemble the third unit