Question

1 Approved Answer

If a painted room is allowed to dry for eight hours before work continues, the result is a delay in the successor activity. The wait

If a painted room is allowed to dry for eight hours before work continues, the result is a delay in the successor activity. The wait for paint to dry is an example of a
a. lead
b. lag
c. mandatory dependency
d. discretionary dependency
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advances In Databases And Information Systems 22nd European Conference Adbis 2018 Budapest Hungary September 2 5 2018 Proceedings Lncs 11019

Authors: Andras Benczur ,Bernhard Thalheim ,Tomas Horvath

1st Edition

3319983970, 978-3319983974

More Books

Students also viewed these Databases questions

Question

=+industrial action Under what circumstances can unions strike?

Answered: 1 week ago

Question

=+What forms of industrial action are common?

Answered: 1 week ago