If during pre-award the procuring contracting officer (PCO) entered three subcontracts in paragraph (j) pf FAR 52.244-2, Subcontracts, what impact will that have on the

If during pre-award the procuring contracting officer (PCO) entered three subcontracts in paragraph (j) pf FAR 52.244-2, Subcontracts, what impact will that have on the contract, post-award? Choose one answer.

  1. The three subcontractors listed in paragraph (j) of FAR 52.244-2 will be exempt from the requirement to provide certified cost or pricing data
  2. The three subcontractors listed in paragraph (j) of FAR 52.244-2 will be required to provide certified cost or pricing data

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding the Law

Authors: Donald L. Carper, John A. McKinsey

6th edition

538473592, 978-0538473590

More Books

Students also viewed these Law questions