If not enough resources are available for a project, to maintain the same project scope and budget, the project team should . . . Question
If not enough resources are available for a project, to maintain the same project scope and budget, the project team should
Question options:
delay some activities until the resource is available.
start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work.
hire additional resources.
accelerate the activities that have enough resources to free the needed resources.