If the audit team established a tolerable rate of deviation of 3%, an expected population deviation rate of 2%, and desired to control the risk
If the audit team established a tolerable rate of deviation of 3%, an expected population deviation rate of 2%, and desired to control the risk of overreliance to 5%, what sample size would be appropriate in this situation?
A. 390 items.
B. 568 items.
C. 590 items.
D. 846 items.