1 Approved Answer

If the normal project cost (before project crashing) is 32 000$ and the overhead cost is 600$ per day, what is the optimal project duration

image text in transcribed

If the normal project cost (before project crashing) is 32 000$ and the overhead cost is 600$ per day, what is the optimal project duration with the least total cost? Justify this answer with a graph of Project duration vs Cost showing three curves: 1) Project cost, 2) Overhead cost, and 3) Total cost = Project cost + Overhead cost.

\begin{tabular}{|c|c|c|} \hline Activity & Maximumreduction(days) & Accelerationcost($/day) \\ \hline A & & \\ \hline B & 6 & 75 \\ \hline C & 5 & 100 \\ \hline D & 4 & 250 \\ \hline E & 3 & 100 \\ \hline F & & \\ \hline G & & \\ \hline H & & \\ \hline I & 2 & 550 \\ \hline J & & \\ \hline K & 2 & 500 \\ \hline L & 4 & 850 \\ \hline M & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods An Introduction For Business Management

Authors: Paolo Brandimarte

1st Edition

978-1-118-0234, 470496343, 470496347, 978-0470496343

More Books

Students also viewed these General Management questions