If the static budget variance is $2,000F, and the flexible-budget variance is $2,200U, what is the sales-volume variance? Select one: a. $200U b. $300U c.
If the static budget variance is $2,000F, and the flexible-budget variance is $2,200U, what is the sales-volume variance? Select one: a. $200U b. $300U c. $200F d. $4,200F