If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources on: A. availability times
If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources on:
A. availability times
B. an as-late-as-possible (ALAP) schedule
C. an as-soon-as-possible (ASAP) schedule
D. a limited schedule plan