If three tasks in a project are estimated to cost $ 1 , 0 0 0 , $ 5 , 0 0 0 , and

If three tasks in a project are estimated to cost $1,000, $5,000, and $10,000 respectively, how should $5,000 worth of contingency funds typically be allocated to cover variability?
1 point
The $5,000 should be allocated to the third task, since it is the highest estimated cost
The $5,000 should be allocated proportionally, with $312.50 for the first task, $1,562.50 for the second task, and $3,125.00 for the third task
The $5,000 should be allocated to the project as a whole
The $5,000 should be split evenly between the tasks, with $1,666.66 going to each task

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Business Continuity Global Best Practices

Authors: Rolf Von Roessing

1st Edition

1931332150, 978-1931332156

More Books

Students also viewed these Accounting questions