If we are using the beta distribution for a three-point estimate in determining activity durations, what would be the duration of the activity below? Most
If we are using the beta distribution for a three-point estimate in determining activity durations, what would be the duration of the activity below? Most likely duration: 3 weeks Optimistic duration: 2 weeks Pessimistic duration: 6 weeks A. 3 weeks B. 3.67 weeks C. 6 weeks D. 3.3 weeks