If we have 4 workstations, a cycle time of 54 sec, and a total task time of 180 sec, the idle time (in sec) would
If we have 4 workstations, a cycle time of 54 sec, and a total task time of 180 sec, the idle time (in sec) would be:
Step by Step Solution
There are 3 Steps involved in it
Step: 1