If you have the following inputs have been used to produce 1,000 units, what is the mullite-factor
Fantastic news! We've Found the answer you've been seeking!
Question:
If you have the following inputs have been used to produce 1,000 units, what is the mullite-factor productivity:
Labor 100 Hours $15/hours
Materials 500 Ibs $5/Ibs
Energy 5,200 kWh $0.15/kWh
Remember the multi-factor productivity= Outputs/ Dollar value of all inputs used.
A.10 units/hour
B. 2 units/Ibs
C. 0.172 units/$
D. 0.209 units/$