Imagine that youre now in time period 17. Activity 4-5 is now complete as scheduled, and Activity 3-6 has also just completed, two periods ahead
Imagine that youre now in time period 17. Activity 4-5 is now complete as scheduled, and Activity 3-6 has also just completed, two periods ahead of schedule. Imagine that Resource A cost $6,000 for each period it was active on Activity 3-6: 5 periods, not the 7 periods at $5,000 per period expected. You are now ahead.
What is the cost variance?
5 - 1-2 1-4 3-6 5-6 Resource Type 2-3 - 4-5 0 1 2 3 4 5 6 7 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Jan 16 Sept 16 Nov 16 Dec 16 Jan 17 May 17 July 17 Aug April 18 5 - 1-2 1-4 3-6 5-6 Resource Type 2-3 - 4-5 0 1 2 3 4 5 6 7 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Jan 16 Sept 16 Nov 16 Dec 16 Jan 17 May 17 July 17 Aug April 18Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started