In 2 0 2 4 , Cupid Construction Company ( CCC ) began work on a two - year fixed price contract project. CCC recognizes

In 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):
Accounts receivable, 12/31/2024(from construction progress billings) $ 37.5
Actual construction costs incurred in 2024 $ 135
Cash collected on project during 2024 $ 105
Construction in progress, 12/31/2024 $ 207
Estimated percentage of completion during 202460%
What are CCC's estimated remaining construction costs on the project at the end of 2024?
Multiple Choice
$0
$135 million
$90 million
$225 million - INCORRECT

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

7th Edition

978-0470477151, 978-0-470-5562, 470556242, 0-470-55624-2, 9780470556245, 978-0470507018

More Books

Students also viewed these Accounting questions

Question

Does your companys code of conduct address this issue?

Answered: 1 week ago