In 2013, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2013, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2015. Information related to the contract is as follows: |
2013 | 2014 | 2015 | |||||||
Cost incurred during the year | $ | 1,776,000 | $ | 3,330,000 | $ | 2,523,400 | |||
Estimated costs to complete as of year-end | 5,624,000 | 2,294,000 | 0 | ||||||
Billings during the year | 1,400,000 | 3,706,000 | 4,894,000 | ||||||
Cash collections during the year | 1,260,000 | 3,000,000 | 5,740,000 | ||||||
Westgate uses the percentage-of-completion method of accounting for long-term construction contracts. |
Required: |
1. | Calculate the amount of gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations.) | |
2013 2014 2015
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started