In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,700,000. Long recognizes revenue over time according to percentage
In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,700,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: |
Balance Sheet | ||||||
Accounts receivable (from construction progress billings) | $ | 31,000 | ||||
Construction in progress | $ | 110,000 | ||||
Less: Billings on construction contract | (107,000 | ) | ||||
Cost and profit of uncompleted contracts in excess of billings | 3,000 | |||||
Income Statement | |||
Income (before tax) on the contract recognized in 2016 | $ | 21,000 | |
Required: | |
1. | What was the cost of construction actually incurred in 2016? |
2. | How much cash was collected in 2016 on this contract? |
3. | What was the estimated cost to complete as of the end of 2016? |
4. | What was the estimated percentage of completion used to calculate revenue in 2016? (Do not round intermediate calculations. Round your percentage answer to 2 decimal places.) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started