Question

1 Approved Answer

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

2016 2017 2018
Cost incurred during the year $ 2,739,000 $ 3,735,000 $ 2,008,600
Estimated costs to complete as of year-end 5,561,000 1,826,000 0
Billings during the year 2,300,000 4,174,000 3,526,000
Cash collections during the year 2,070,000 3,900,000 4,000,000

Westgate Construction uses the completed contract method of accounting for long-term construction contracts.
Required:
1.

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Loss amounts should be indicated with a minus sign.)

Revenue

Gross profit (loss)

2-a.

In the journal below, complete the necessary journal entries for the year 2016 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

Record the construction costs.

Record the progress billings.

Record the cash collections.

Record the gross profit.

2-b.

In the journal below, complete the necessary journal entries for the year 2017 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

Record the construction costs.

Record the progress billings.

Record the cash collections.

Record the gross profit.

2-c.

In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

Record the construction costs.

Record the progress billings.

Record the cash collections.

Record the gross profit.

3.

Complete the information required below to prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.

Current Assets 2016 2017

Current Liabilities 2016 2017

4.

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Loss amounts should be indicated with a minus sign.)

2016 2017 2018
Cost incurred during the year $ 2,430,000 $ 3,815,000 $ 3,230,000
Estimated costs to complete as of year-end 5,630,000 3,130,000 0

Revenue

Gross Profit (loss)

5.

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Loss amounts should be indicated with a minus sign.)

2016 2017 2018
Cost incurred during the year $ 2,430,000 $ 3,815,000 $ 3,945,000
Estimated costs to complete as of year-end 5,630,000 4,130,000 0

Revenue

Gross profit (loss)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions