Question

1 Approved Answer

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

2016 2017 2018
Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400
Estimated costs to complete as of year-end 5,041,000 2,414,000 0
Billings during the year 2,190,000 2,496,000 5,314,000
Cash collections during the year 1,895,000 2,400,000 5,705,000

Westgate recognizes revenue over time according to percentage of completion.

Required:

Calculate the amount of revenue and gross profit to be recognized in each of the three years

2.

Record construction costs for all 3 years

Record progress billings for all 3 years

Record cash collections for all 3 years

Record gross profit for all 3 years

3. Complete the information required below to prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities.

4.

Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2016 2017 2018
Cost incurred during the year $ 2,059,000 $ 3,895,000 $ 3,295,000
Estimated costs to complete as of year-end 5,041,000 3,195,000 0

5.

Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2016 2017 2018
Cost incurred during the year $ 2,059,000 $ 3,895,000 $ 4,185,000
Estimated costs to complete as of year-end 5,041,000 4,290,000 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools for business decision making

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

6th Edition

978-0470477144, 1118096894, 9781118214657, 470477148, 111821465X, 978-1118096895

More Books

Students also viewed these Accounting questions

Question

3. What is a pop-up blocker and why is it needed?

Answered: 1 week ago