In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020

Cost incurred during the year $2,624,000 $3,690,000 $2,074,600

Estimated costs to complete as of year-end 5,576,000 1,886,000 0

Billings during the year 2,200,000 4,114,000 3,686,000

Cash collections during the year 2,000,000 3,800,000 4,200,000

Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Auditing An Evolving Agenda

Authors: Jagdish Pathak

1st Edition

3642060579, 978-3642060571

More Books

Students also viewed these Accounting questions