Question

1 Approved Answer

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,550,000 $ 4,250,000 $ 1,870,000
Estimated costs to complete as of year-end 5,950,000 1,700,000 0
Billings during the year 2,050,000 4,750,000 3,200,000
Cash collections during the year 1,825,000 4,100,000 4,075,000

Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
Cost incurred during the year $ 2,550,000 $ 3,825,000 $ 3,225,000
Estimated costs to complete as of year-end 5,950,000 3,125,000 0

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
Cost incurred during the year $ 2,550,000 $ 3,825,000 $ 3,975,000
Estimated costs to complete as of year-end 5,950,000 4,150,000 0

Requirement 1

2018 2019 2020
Revenue
Gross profit (loss)

Requirement 2A

Record construction costs - Record progress billings - Record cash collections - Record gross profit (loss)

Date General Journal Debit Credit
2019

Requirement 2B

Record construction costs - Record progress billings - Record cash collections - Record gross profit (loss)

Date General Journal Debit Credit
2019

Requirement 2C

Record construction costs - Record progress billings - Record cash collections - Record gross profit (loss)

Date General Journal Debit Credit
2019

Requirement 3

Balance Sheet (Partial) 2018 2019
Current assets:
Current liabilities:

Requirement 4

2018 2019 2020
Revenue
Gross profit (loss)

Requirement 5

2018 2019 2020
Revenue
Gross profit (loss)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ronald W Hilton

7th Edition

0073022853, 978-0073022857

More Books

Students also viewed these Accounting questions

Question

Calculate the cost of goods sold? r at r - 1,1 11,=1

Answered: 1 week ago