Question

1 Approved Answer

In 2021, the Eastgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to

In 2021, the Eastgate Construction Company entered into a contract to construct a bridge for $12,000,000.

The bridge was completed in 2023. Information related to the contract is as follows:

2021 2022 2023

Cost incurred during the year $1,840,000 $3,760,000 $4,500,000

Estimated costs to complete as of year-end $6,160,000 $4,400,000 $0

Billings during the year $2,700,000 $4,300,000 $5,000,000

Cash collections during thee year $2,600,000 $3,900,000 $5,100,000

Eastgate recognizes revenue over time according to the percentage of completion method.

What amount will Eastgate report on the balance sheet at 12/31/2021 for "Costs and profits in excess of billings"?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

T F Line positions support staff positions in decision making.

Answered: 1 week ago

Question

Evaluate the impact of unions on nurses and physicians.

Answered: 1 week ago

Question

Describe the impact of strikes on patient care.

Answered: 1 week ago

Question

Evaluate long-term care insurance.

Answered: 1 week ago