Question
In 2021, the Eastgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to
In 2021, the Eastgate Construction Company entered into a contract to construct a bridge for $12,000,000.
The bridge was completed in 2023. Information related to the contract is as follows:
2021 2022 2023
Cost incurred during the year $1,840,000 $3,760,000 $4,500,000
Estimated costs to complete as of year-end $6,160,000 $4,400,000 $0
Billings during the year $2,700,000 $4,300,000 $5,000,000
Cash collections during thee year $2,600,000 $3,900,000 $5,100,000
Eastgate recognizes revenue over time according to the percentage of completion method.
What amount will Eastgate report on the balance sheet at 12/31/2021 for "Costs and profits in excess of billings"?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started