Question
In 2021, the W Construction Company entered into a contract to construct a road for SC County for $10,000,000. The road was completed in 2023.
In 2021, the W Construction Company entered into a contract to construct a road for SC County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
W recognizes revenue over time according to percentage of completion.
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)
**the current liabilities are as follows: accounts receivables, construction in progress, less: billings, costs and profit in excess of billings and there is one current liability that I don't know - so please include that and the numerical information**
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started