Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

In 2021, the W Construction Company entered into a contract to construct a road for SC County for $10,000,000. The road was completed in 2023.

In 2021, the W Construction Company entered into a contract to construct a road for SC County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800
Estimated costs to complete as of year-end 6,020,000 1,978,000 0
Billings during the year 2,060,000 4,562,000 3,378,000
Cash collections during the year 1,830,000 4,200,000 3,970,000

W recognizes revenue over time according to percentage of completion.

3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

**the current liabilities are as follows: accounts receivables, construction in progress, less: billings, costs and profit in excess of billings and there is one current liability that I don't know - so please include that and the numerical information**

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Xbrl Financial Reporting In The 21st Century

Authors: Bryan Bergeron

1st Edition

0471220779, 978-0471220770

More Books

Students also viewed these Accounting questions