In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023

Cost incurred during the year: $2,580,000 $4,042,000 $2,175,800

Est. costs- complete for year-end: 6,020,000 1,978,000 $0

Billings during the year 2,060,000 4,562,000 3,378,000

Cash collections during the year: 1,830,000 4,200,000 3,970,000

Westgate recognizes revenue over time according to percentage of completion.

Required:

1.Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.(Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting, The Financial Chapters

Authors: Tracie Miller Nobles

12th Edition

013449041X, 9780134490410

More Books

Students also viewed these Accounting questions

Question

What reward will you give yourself when you achieve this?

Answered: 1 week ago