Question

1 Approved Answer

In 2022 , Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in

image text in transcribed
image text in transcribed
image text in transcribed
In 2022 , Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the following bar chart. Assuming $5,000 indirect cost per month, and 11.4% markup. If the retainage is 9% throughout the project, finance charge is 1% per month, and payments will be billed at the end of the month and will bereceived one month later. How much is the last payment the contractor is expected to receive? \begin{tabular}{|l|l|l|l|l|l|l|l|} \hline End of Month & 0 & 1 & 2 & 3 & 4 & 5 \\ \hline Monthly Cost (Direct \& Indirect Cost) & & & & & & & \\ \hline Monthly Billing & & & & & & & \\ \hline Monthly Income & & & & & & & \\ \hline Retainage & & & & & & & \\ \hline Overdraft before interest) & & & & & & & \\ \hline Interest (1\%) & & & & & & & \\ \hline Overdraft (deduct interest) & & & & & & \\ \hline Overdraft (add income) & & & & & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Public Finance Lessons From The Past And Effects On The Future

Authors: Miguel-Angel Galindo Martin

1st Edition

1629481491, 978-1629481494

More Books

Students also viewed these Finance questions

Question

What are the criteria to recognize revenue?

Answered: 1 week ago

Question

List all the correct attributes of the square root parent function

Answered: 1 week ago