Question
In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the
In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the following bar chart.
1)Assuming $5,000 indirect cost per month, and 13.2% markup. If the retainage is 6% throughout the project, finance charge is 1% per month, and payments will be billed at the end of the month and will be received one month later. How much is the last payment the contractor is expected to receive?
2) Fill Table
End of Month 0 1 2 3 4 5 Monthly Cost (Direct & Indirect Cost) Monthly Billing Monthly Income Retainage Overdraft (before interest) Interest1% Overdraft (deduct interest) Overdraft (add income)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started