Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

In 2024, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,000,000. Long recognizes revenue over time according to percentage

In 2024, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,000,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2024, is as follows:

Balance SheetAccounts receivable (from construction progress billings) $ 44,000Construction in progress$250,000 Less: Billings on construction contract(242,000) Cost and profit of uncompleted contracts in excess of billings 8,000Income StatementIncome (before tax) on the contract recognized in 2024$ 34,000

Required:

  1. What was the cost of construction actually incurred in 2024?
  2. How much cash was collected in 2024 on this contract?
  3. What was the estimated cost to complete as of the end of 2024?
  4. What was the estimated percentage of completion used to calculate revenue in 2024?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: David Perkins

4th Edition

111925700X, 978-1119257004

More Books

Students also viewed these Accounting questions