Question
1 Approved Answer
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cash collections during the year Billings during the year 2024 $ 2,072,000 5,328,000 2,160,000 2025 $ 2,738,000 2,590,000 2,650,000 2026 $ 2,849,000 1,880,000 2,700,000 5,190,000 5,420,000 Westgate recognizes revenue over time according to percentage of completion. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs ncurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts hould be indicated with a minus sign. Costs incurred during the year Estimated costs to complete as of year-end 2024 $ 2,072,000 5,328,000 2025 $ 3,880,000 3,180,000 2026 $ 3,280,000
Step by Step Solution
★★★★★
3.31 Rating (151 Votes )
There are 3 Steps involved in it
Step: 1
To calculate the amount of revenue and gross profit or loss to be recognized for each of the years 2024 2025 and 2026 well use the percentage of compl...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3