In 20X5, Build-It Corp. (BIC) was awarded a fixed-price contract of $9,400,000 to construct a warehouse for a client. Work began in 20X5 and was

In 20X5, Build-It Corp. (BIC) was awarded a fixed-price contract of $9,400,000 to construct a

warehouse for a client. Work began in 20X5 and was completed in 20X7. BIC originally

estimated the project costs at $8,500,000. A schedule of actual costs and revised estimates,

together with progress billings and collections, follows:

(in $'000s) 20X5 20X6* 20X7**

Cumulative costs incurred 1,900 6,400 8,800

Estimated costs to complete 6,800 2,800 0

Progress billing during the year 2,200 6,800 400

Collections during the year 1,500 7,000 900

* This revised cost data was not known in 20X5.

** This revised cost data was not known in 20X6.

BIC reports its financial results in accordance with IFRS. Its year end is December 31. It uses

the cost-to-cost method to determine construction revenue. Project completion is considered a

single performance obligation that will be satisfied over time.

What are required summary journal entries complete with explanations for each of the 20X5,

20X6, and 20X7 fiscal years. (Round the percentage of completion to one significant decimal

place for example, 16.4% to determine the amount of revenue to be recognized in each

year.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

9781119563099

Students also viewed these Accounting questions