In a batch machining operation on a conventional machine, setup time is 1 . 5 hours and batch size is 8 0 units. The cycle

In a batch machining operation on a conventional machine, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of 30 sec and processing time of 1.37 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 2.0 min. The reliability of this machine is characterized by mean time between failures of 37 hours and a mean time to repair of 55 min.
Determine
a) Average cycle time
b) Time to complete the batch
c) Average hourly production rate of the machine if availability is ignored.
d) Average hourly production rate of the machine if availability is taken into account.
e) Suppose that availability only applied during the actual run time of the machine and not the setup time. Determine the average hourly production rate of the machine

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Michael A. Hitt, Stewart Black, Lyman W. Porter

3rd edition

132553287, 978-0132553285

More Books

Students also viewed these General Management questions

Question

For 2016, how can the amount of the sales tax deduction determined?

Answered: 1 week ago