In a certain standard costing system, the following results occurred last period: labour rate variance, $1,000 unfavourable; labour efficiency variance, $2,800 favourable; and the actual
In a certain standard costing system, the following results occurred last period: labour rate variance, $1,000 unfavourable; labour efficiency variance, $2,800 favourable; and the actual labour rate was $0.40 more per hour than the standard labour rate. What number of actual direct labour hours was used last period?
4,800 hours. | ||
5,000 hours. | ||
5,400 hours. | ||
2,500 hours. |