In a meeting to gain approval of the quality management plan, a stakeholder points out what he believes to be an error in the plan.
In a meeting to gain approval of the quality management plan, a stakeholder points out what he believes to be an error in the plan. He notes that the plan includes using some of the same techniques can be used in two of the three quality management processes?
Group of answer choices
Logical data model
Checklists
Interviews
Checksheets
Causeandeffect diagrams