In a network diagram, the backward pass is used to: a . Calculate the Late Start ( LS ) and Late Finish ( LF )
In a network diagram, the backward pass is used to:
a
Calculate the Late Start LS and Late Finish LF times
b
Determine the Early Start ES and Early Finish EF times
c
Calculate float for each activity.
d
Identify critical activities