In a project network A-B-D-F-H is a critical path. If activity C is delayed by 2 days having slack 2. What will happen? Select one:

image text in transcribed
In a project network A-B-D-F-H is a critical path. If activity C is delayed by 2 days having slack 2. What will happen? Select one: a. Project will be delayed by 2 days b. Project will be on-time c. Project may be delayed by 2 days