In a work breakdown structure (WBS), a unit of work may appear in more than one location in the WBS because the work may be
In a work breakdown structure (WBS), a unit of work may appear in more than one location in the WBS because the work may be considered in multiple contexts (e.g. a task might be associated with plumbing and also be associated with the kitchen). Group of answer choices True False