In BTEC 3 2 7 , you have been told you can only build your project during your lab time. What type of predecessor is

In BTEC 327, you have been told you can only build your project during your lab time. What type of predecessor is this an example of?
Mandatory predecessor
Discretionary predecessor
Internal predecessor
External predecessor
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render, Paul Griffin

1st Canadian Edition

132687585, 978-0133357516, 133357511, 978-0132687584

More Books

Students also viewed these General Management questions

Question

WHAT IS ACCOUNTING AND FUNCTIONS?

Answered: 1 week ago

Question

Breathing explain?

Answered: 1 week ago

Question

WHAT IS DOUBLE ENTRY ACCOUNTING SYSTEM?

Answered: 1 week ago