Question
1 Approved Answer
(in dollars) Current Period Cummulative To Date At Complete BCWS BCWP ACWP SV CV BCWS BCWP ACWP SV CV SPI CPI BAC EAC (EAC) VAC
(in dollars) Current Period Cummulative To Date At Complete BCWS BCWP ACWP SV CV BCWS BCWP ACWP SV CV SPI CPI BAC EAC (EAC) VAC % Spent EAC % Complete Control Accounts - ABC123 Project Mgr: Student Work Package A 0 0 0 0 0 262 262 262 0 0 1 1 262 262 0 1.00 100 Work Package B 5,000 4,500 6,000 -500 -1,500 103,911 99,000 109,008 -4,911 -10,008 1 1 103,911 111,500 -7,589 0.98 95 Work Package C 475 400 520 -75 -120 101,204 106,222 96,802 5,018 9,420 1 1 110,000 110,000 0 0.88 97
Step by Step Solution
There are 3 Steps involved in it
Step: 1