In estimating the project duration, the project manager learned that it might take an optimistic time of 6 days, molikely time of 12 days, and
In estimating the project duration, the project manager learned that it might take an optimistic time of 6 days, molikely time of 12 days, and a pessimistic time of 24 days. evaluate the PERT weight average