In Feb. 2018, Siemens Engineering Co. signed a $240 million contract to construct a new city hall within two years. The city will pay $180

In Feb. 2018, Siemens Engineering Co. signed a $240 million contract to construct a new city hall within two years. The city will pay $180 million within six months, and the rest $60 million one year later.

Siemens expects that total cost would be $180 million, with $72 million costs incurred during 2018, and rest of the cost will incur in 2019.

A). Using the cost-to-cost method, how much revenue should Siemens recognize in 2018 and 2019 respectively? What is the recognized gross profit in 2018 and 2019?

B). If in Feb. 2018, Siemens deliberately under-estimates the total construction cost as only $160 million. Assume everything else about the project remains unchanged, what would be the recognized gross profit in 2018 and 2019 instead?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

State Owned Enterprise In The Western Economies

Authors: Raymond Vernon , Yair Aharoni

1st Edition

0415727596,1317917685

More Books

Students also viewed these Finance questions

Question

Cost Accounting: Please help me with all requirements

Answered: 1 week ago

Question

=+a. What would a fair insurance policy cost?

Answered: 1 week ago

Question

Family basic steps to socialization write a short note ?

Answered: 1 week ago

Question

What does physics deal with?

Answered: 1 week ago

Question

Enumerate the qualities of a salesman.

Answered: 1 week ago