Question

1 Approved Answer

in IT Project Managment Q1) a. A project has five stakeholders, when an additional project member gets added, how many communication channels exist? (1 Mark)

in IT Project Managment

Q1)

a. A project has five stakeholders, when an additional project member gets added, how many communication channels exist? (1 Mark)

b. The project manager intends to get a module completed within a deadline but there are few reluctant team members who dont intend to comply with the manager. What strategies can the manager use to resolve the potential disagreements? (1 Mark)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Power Bi And Azure Integrating Cloud Analytics For Scalable Solutions

Authors: Kiet Huynh

1st Edition

B0CMHKB85L, 979-8868959943

Students also viewed these Databases questions

Question

9. Explain the relationship between identity and communication.

Answered: 1 week ago

Question

a. How do you think these stereotypes developed?

Answered: 1 week ago

Question

a. How many different groups were represented?

Answered: 1 week ago