Question

1 Approved Answer

In January. 2 0 2 1 , Siemens Engineering Co . signed a $ 2 4 0 million contract to construct a new city hall

In January. 2021, Siemens Engineering Co. signed a $240 million contract to construct a new city hall within two years. The city will pay $180 million upfront, and the rest $60 million at the end of the project.
Siemens expects that total cost associated with the project would be $180 million, with $72 million costs incurred during 2021, and rest of the cost will incur in 2022.
Using the cost-to-cost method, how much revenue should Siemens recognize in 2021 and 2022 respectively? What is the recognized gross profit each year?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Applying the CosttoCost Method Siemens is using the costtocost method to recognize revenue and profi... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Precalculus

Authors: Michael Sullivan

9th edition

321716835, 321716833, 978-0321716835

More Books

Students also viewed these Accounting questions

Question

Plot point given in polar coordinates. (2, -5 /4)

Answered: 1 week ago